We are currently doing most of the work within the
Atlanta Metro area. These comprise of, but are not
limited to various demolition projects to enable
the expansion and modernization of Hartsfield-Jackson
Atlanta International Airport, the primary airport
in the Southeast United States and busiest in the
nation in terms of passenger traffic.
Specific projects at the Airport include demolition
of 340,000 ft of warehouse buildings close to the
still functioning runway. These buildings include
the Gate gourmet facilities, approximately 113,453
ft in area and 25 ft in height, and Old Eastern cargo
facilities, approximately 216,800 ft in area and
30 ft in height and most recently the Old FAA Control
Tower. Among our challenges were working next to
a still functioning runway, security, dust and debris
control. |